The Library – A Case History in Mismanagement
Key points:
- The price for both the library and science center
went up well beyond the original projections. Only one
board member at one meeting voted to limit costs.
- Colgate makes much of the cost of materials and inflation as the
cost of the overrun. There is no mention of unrealistic
expectations to
keep the library open during construction, changing
architects, redesigning the plans, starting over, etc. These
are actions that one would expect to be recorded and approved by the
Trustees as a body but they are glossed over and barely mentioned in minutes.
- Cost overruns and flexible guarantees are but two
of numerous failings. The original completion date for Case was
fall of 2005, a deadline that was missed by
almost two years. The Class of 2007 was without a library
for their junior year and all but two months of their senior year.
- The hiring of an outside construction manager on the eve of breaking ground was not enough to save the project as originally envisioned by a committee of university administrators. This committee had little or no construction experience, yet had been tasked with overseeing one of the most complicated American university library projects ever undertaken.
Timeline for Case Library and Information Center (CLIC)
January 10-13, 1999
The building committee chairman recommends a study to be made of the proposed Case Library expansion before decisions are made. This good advice, if followed, may have prevented costly mistakes.
May 18, 2001
Colgate University President Karelis said, “The various
projects (library and science center) add up to more than one might expect,
and there
might be more pressing needs than buildings.”
January 9, 2002
Treasurer David Hale reports the anticipated budget for Case Library renovations to be $37 million - $40 million.
March 19, 2002
CLIC project in competing architect presentation stage. The winning
firm, Pickard-Chilton Architects, had never designed a state-of-the art
university library.
May 18, 2002:
Treasurer David Hale reports, "Case Library Renovation/Expansion
estimated to cost $40 million with the vast majority
of the expenditures expected to occur from fiscal 2002-03 through 2004-05.”
Sept. 28, 2002
Constraints influencing the design as well as the process to reconcile
program and project costs to meet the budget of $40 million are
reviewed.
Nov. 22, 2002
Maroon News cites a projected increase to $45 million for
the original estimate of $40 million.
January 8, 2003
The Board of Trustees agrees to spend
an additional $5 million to repair the library facade and roof.
Editor’s Comment: How did the architects or Colgate’s
maintenance department miss that the existing building would require
$5 million in repairs? Ultimately, the building was replaced,
not renovated, so the $5 million – and finally $21 million
- that was added to the cost did not include a repair to the roof.
January 25, 2004
Proposed design for Case Library and Info Tech Center approved for $43.5
M.
March 28, 2004
Construction manager hired. Colgate has raised $8 million of
the $10 million needed to meet Mr. Benton’s $10 million challenge
for funding CLIC.
May 15, 2004
Groundbreaking ceremony for CLIC
Oct. 9, 2004
Cost limits set: $45M-$47M for Case Library
November 9, 2004
More than two and half years after
Pickard-Chilton Architects win the contract, the project stops and a
new team of Shepley Bulfinch Richardson and Abbot, Architects of Boston. The
project is largely scrapped and new plans are developed.
November 17-18, 2004
Treasurer’s Report by David Hale: renovation of Case Library ($45
million)
January 30, 2005
The Case Library project, with 100% completion of the schematic design,
has a new budget estimate of $50.3 million and a guaranteed
maximum price date of May 2005.
May 14, 2005
Case Library and Center for Info Technology construction estimate at $51.8M,
plus $550K for green and terraced roofs (revised upward from Jan 2005
estimate). These estimates do not include associated campus
infrastructure work of approximately $5 M.
December 2005
Construction re-starts with new plans.
Sept 30, 2006
The Board determines that operating costs of the Case Library will come
from campaign gifts and “aggressive price increases.” The
board approved, with one opposing vote, raising the budget on Case
Library from $52.5M to $57.5M.
March 17, 2007
Case Library and Information Center opens just two months
before the Class of 2007 will graduate. The original completion
date was the fall of 2005.
November 6, 2007
Board of Trustees approves $60.4
million for all costs
associated with the renovation and expansion of CLIC. An additional
$3 million contingency was set-aside for any additional costs of finishing
the two structures.
Background
In 2000, Mark Spiro was
hired by Colgate University as vice president for administrative services.
Spiro left a 22-year career at Cornell College School of Engineering
where he held various management positions including associate dean in
the School of Engineering. At Cornell, he led “faculty, administration and building professionals through
the conceptual and design phases for Duffield Hall, a $62.5 million project.” Spiro
left Cornell for Colgate before Duffield Hall was finished in the fall
of 2004, about 15 months past the originally completion date.
At Colgate, Mark Spiro led the team that hired Pickard
Chilton Architects Inc., of New Haven, CT, as the initial design architects
for the Case Library project. They won the contract even though the firm
had no experience in designing a state-of-the art library and information
center. Anthony Markese of Pickard Chilton was the design principal. Kendall/Heaton
Associates Inc., of Houston was the architect of record.
Colgate had several criteria for the library. They
didn’t want to move any off-sight storage of materials. This
necessitated an automated retrieval system, which required a state-of-the-technology
system. They didn’t want the library closed down while the “renovation” was
underway. This second criteria, and the idea that the library
was a renovation, as opposed to new construction, created
a lot of pressure on the staff, students and contractors. At one
point, the college issued earplugs to students to help decrease the noise
level of workers jack hammering in the basement.
Archived files were housed in off-site locations and were unavailable
to access for about two years. The staff was constantly working
around the construction.
The original construction project for Case broke ground May
15, 2004. Pickard Chilton spent several million dollars
trying to beef up the structure, but within six months, it was clear
there was a problem with the plan. “A mutual decision that Pickard
Chilton would withdraw from the design team was solely due
to a change in the University’s aesthetic objectives relating
to a portion of the exterior of the building.” Maroon News
11/12/2004. Details about the project have been scrubbed from
the Pickard Chilton website.
The original plan included a winter garden on the fifth floor of the
library, which caused the staff great concern about what would happen
to the books if there should be a leak.
New architects were hired, Shepley Bulfinch Richardson
and Abbot, Architects of Boston. They recommended scrapping the
entire project and starting over. At one point, it was suggested
that the library remain open during the demolition. The staff
protested that they wouldn’t have walls and it was agreed that
the library staff would move out.
The interim library was housed in the James B. Colgate
Hall, Donovan’s Pub, and the former Cutten Dining Hall. The Edge
and Frank Dining Halls were kept open late during finals and peak study
times.
The plan was halted for six months while new plans
were drawn and the project restarted. The project re-started
in December 2005. The library opened March 18, 2007,
to counter the charge by graduating seniors that they had been
without a library in their junior and senior years at Colgate.
The automated retrieval system was built. Approximately 400,000 books/tapes/films
etc. are stored in the huge vault, which is located on the water run-off
side of the hill, a concern for staff.
The Library is designed as a “Smart” building. Windows
do not open and the heating control for the whole building is run from
a single source. Temperatures inside the building may range from
50 to 90 in the same day throughout the building. The lights are
on 24/7 because there are no light switches. The lights will go
off in offices in personnel sit still for too long. There are
no obvious overrides for heat or light control. Exterior doors on fifth
floor (accessible by a bridge) “can’t be locked and keep
the building open by utilizing only the level 3 exits, since anyone passing
by the motion detector will automatically unlock it because it is designed
as a fire egress for security reasons” Maroon News 2/14/08.
The offices were designed without input from personnel who be using
them. Electrical outlets are oddly situated and many staff members
have extension cords running across floors and desks. As the project
wore on and costs mounted, there were efforts to cut back on expenses. One
example: the balconies around the building are not coded as sufficiently
strong enough for people to stand on, even though there are doors leading
to them. The doors are considered fire exits.
Mark Spiro left Colgate shortly before the Ho Science Center was near
completion. Presumably, he was bought-out of his contract. He is
no longer listed in the Colgate directory. Joe Bello was the initial
project manager. Physical Plant Project Manager Vito Bolognone
was named project manager by Nov. 2006.
|